title: "Northern sewer works paused as Maufant homes take priority"
url: https://www.nsfw.info/northern-sewer-works-paused-maufant-homes-priority/
published: 2026-11-17T12:30:50+00:00
modified: 2026-11-17T12:30:50+00:00
author: "Chief Editor"
categories: ["Government"]
image: https://www.nsfw.info/wp-content/uploads/2026/11/northern-sewer-works-paused-maufant-homes-priority-1024x572.webp
summary: "Phase 1C of Jersey's northern sewer upgrades is being paused so resources can be redirected to a 30-home affordable housing site at Maufant."
publisher: NSFW (https://www.nsfw.info)
---

# Northern sewer works paused as Maufant homes take priority

**In brief:** The next phase of sewer upgrades north of Sion is being paused so that staff and resources can be redirected to support a 30-home affordable housing development at Maufant. Infrastructure Minister Jonathan Renouf confirmed the “significant adjustment” at a budget review hearing, offering some relief to businesses already battered by the existing St John roadworks. The current phases remain on track for completion in spring 2027.

## A Tale of Two Trenches

Jersey’s northern parishes have been living with the disruption of sewer upgrade works since November 2025, and for businesses along the St John corridor, it has not been a pleasant experience. The Jersey Evening Post reports that one store owner previously warned the impact of the works could be “similar to that of Covid”, with lanes she described as “littered with one-way and no-entry signs and arrows” that “don’t tell you anything”. Strong words, and not the kind of review any infrastructure department wants pinned to its noticeboard.

Now, Infrastructure Minister Deputy Jonathan Renouf has confirmed to the Environment, Housing and Infrastructure budget review panel that money allocated to Phase 1C of the northern sewer network programme will instead be redirected to upgrade work required to support a 30-home affordable housing development at Maufant, on La Rue des Buttes just south of St Martin’s Catholic Church. When panel chair Deputy Hilary Jeune asked directly whether Phase 1C north of Sion would be stopped for now, Deputy Renouf replied: “For now, yes, because there’s a more pressing need at Maufant.”

## The Maufant Development

The Maufant site has had a bumpy road to approval. The former Planning Committee refused the application in March 2025, but that decision was overturned on appeal after Planning Minister Sir Mark Boleat accepted a recommendation from independent planning inspector Nigel McGurk. The site was specifically rezoned for affordable housing in the Bridging Island Plan.

The proposed development comprises 30 homes, including 12 two-bedroom and 18 three-bedroom properties. Under the original application, the homes are intended to be transferred to Jersey Homes Trust, with 55% available for affordable purchase and 45% for social rent. A small number of homes for elderly, low-income parishioners are also included through arrangements involving the Sir David Kirch Trust.

The housing development itself is due to begin in 2028, but Ellen Gallichan, group director of Operations, Transport and Sport, told the panel that the associated sewer works could run on until 2029. She said the department would be “very mindful to try and minimise disruption” to businesses and residents, drawing lessons from the St John works. Whether those lessons will translate into clearer signage remains to be seen.

## What This Means for the North

There is a silver lining of sorts for the beleaguered businesses north of St Helier. A spokesperson for the Infrastructure and Environment Department confirmed that once Phases 1A and 1B of the northern sewer upgrades are complete, the road will be cleared. Those phases remain on track for completion by April and May 2027 respectively, according to the Jersey Evening Post.

Deputy Renouf acknowledged that postponing Phase 1C would bring “some relief” to those affected by the existing roadworks. For a business owner who has spent the past year watching customers navigate a maze of contradictory signs, that will be welcome news, even if the relief arrives rather late.

The decision follows a question from panel member Deputy Alex Curtis about whether planned investment in liquid-waste infrastructure still matched the need for upgrades and capacity for new housing. The answer, it turns out, is that the two demands are now in direct competition, with housing taking priority.

## The NSFW Perspective

There is something quietly revealing about this episode. A major infrastructure programme, already causing significant hardship to local businesses, is being paused mid-sequence so that resources can be diverted to support a housing development that will not even begin construction until 2028, with the associated sewer works potentially running until 2029. That is a long time to keep a spade in the ground for homes that are still years away.

One might ask whether a more joined-up approach to planning and infrastructure investment could have avoided this particular game of musical diggers. When a department describes redirecting a major capital programme as a “significant adjustment”, it is worth wondering whether the original plan was as robust as it should have been. Businesses in St John have already paid a considerable price for the disruption. They deserve better than to find out mid-project that the sequel has been cancelled.

*Source: [Jersey Evening Post](https://jerseyeveningpost.com/news/2026/11/17/northern-sewer-upgrades-to-be-put-on-hold-as-maufant-housing-takes-priority)*